CHALLENGE
Spiralling costs and interrupted supplies of CO2 prompted Wells & Co, a leading craft brewer, to find a partial alternative to CO2 for their production processes.
SOLUTION
Nitrogen replaced CO2 at many stages of the brewing process. Following a detailed scoping and sizing exercise, Parker’s standalone NITROSource system was easily installed on site and generates nitrogen at a fraction of the cost of CO2.
BENEFITS
CO2 consumption has reduced by over 50 tonnes per year, a saving of around 73% in costs per cubic metre for the site. It has resulted in the brewery's single biggest reduction in carbon emissions.
REPLACING CO2 WITH NITROGEN REDUCES RELIANCE ON CO2 AND SAVES 73% IN COSTS PER CUBIC METRE.
CO2 shortages have hit breweries hard in recent years. It’s used throughout production so interrupted supplies can often cause output issues and may push prices up.
The energy crisis has made the situation worse. The rising cost of gas recently prompted CF Industries to halt ammonia production at their Billingham plant, meaning that the production of CO2 at the plant will also cease. Where CO2 is available, brewers are seeing huge price increases.
Wells & Co, a leading craft brewer, produces 25,000 hectolitres of beer at its Bedfordshire plant, using 500 kg of CO2 each day. While their CO2 costs were contracted, the contractual price is linked to supply and if CO2 becomes hard to get hold of, the cost rises. Wells & Co didn’t experience production downtime because of CO2 shortages, but this was only because they were able to buy gas in bulk.
James Hunter, Lead Brewer at Wells & Co says: “We generally buy in enough CO2 at a time to cover twice our monthly production, but that’s something smaller breweries simply can’t do. Supply shortages are a real problem for many brewers.”
Lowering costs and reducing reliance on CO2 were key business objectives. Nitrogen can replace CO2 in some processes and with Parker’s NITROSource, it can be generated on demand at a fraction of the cost of buying in gas. While the level of dissolved oxygen (DO) produced must be considered, any potential degradation of product quality is assessed in the initial scoping exercise.
“It was straightforward.” The scoping and sizing exercise calculated existing gas usage, taking into account the link between peak demands, purity and buffer capacity. “If you get your calculations right, the installation should be straightforward,” says James. “It’s literally plug and play for the unit, then you just have the electrical supply and peripherals like the pipework to manage.”
James Hunter, Head Brewer, Wells & Co
“The capital investment doesn’t just include the unit – we also have to consider energy consumption, ancillary equipment and maintenance. That said, we’ll see a return on our investment within 2 ½ years and it’s made us more cost-competitive. The contribution to our environmental objectives has more than exceeded our expectations.”
James Hunter, Head Brewer, Wells & Co